The Plan
Construct a street legal, Shelby Cobra 427 replica for around $20,000 and complete it at a tolerable pace.   Authenticity and period accuracy is not my primary goal; safety, performance and reliability are.  Car will serve as a daily driver. The build is focused not only on completing the vehicle but enjoyment of the build process. 

May 2001
Pick up kit                                                       COMPLETE
Inventory                                                            COMPLETE
Body and Aluminum Panel Removal      COMPLETE

June 2001
Front Suspension                                          COMPLETE
Steering Rack                                                  COMPLETE
Battery                                                              COMPLETE

July 2001
TDY to Ft Belvoir

August 2001
Rear End                                                            COMPLETE
Fuel Tank and Filter                                        COMPLETE
Pedal Box and Pedals                                  COMPLETE
Master Cylinder and Push Rod                    COMPLETE
Aluminum-Floor Panels                                 COMPLETE
Aluminum-Footboxes                                    COMPLETE

September 2001
Fuel, Brake and Battery Lines                     COMPLETE          
Engine Preparation                                          COMPLETE 12/12/01
Engine Installation                                           COMPLETE 1/21/02                    

October 2001
Accelerator and Clutch Cable                      COMPLETE 1/26/02
Mass Air and Fuel Vapor Canister             COMPLETE 1/27/02
Radiator, Hoses and Fan Shroud               COMPLETE 2/2/02
Wiring Harness and EEC IV

November 2001
Gauges and Pod Installation                        N/A
Aluminum Trunk and Sidewall
Emergency Brake                                           COMPLETE 3/14/02
Steering shaft and pillow block                    COMPLETE 3/14/02
Wheels, tires and ride height                       COMPLETE 3/14/02
Checking the running gear                           COMPLETE 3/14/02
FIRST FIRE (Hopefully)                                 COMPLETE 3/14/02                              

July 2002
Footbox Top
Rubber Aluminum Edge Seal                      COMPLETE 9/14/02
Roll Bar Drilling                                               COMPLETE 9/15/02
GO KART COMPLETE                                 COMPLETE 8/31/02
                    
August 2002
Body Mounting                                                  COMPLETE 11/15/02
Initial Body Prep                                              COMPLETE 11/9/02
Trunk-License Plate Light                              COMPLETE 11/18/02                              
Trunk-Latch
Hood Handles
Badges
Fuel Neck and Gas Cap
Windshield
Side View Mirror

November 2002
Doors and Hinges
Check Straps
Aluminum-Nose Floor and Walls
Aluminum-Cockpit and Trunk
Side Exhaust
Roll Bar
Rear View Mirror
Seats
Body Prep

December 2002
Christmas Vacation!

January 2003
Body to the painter
Dash and Gauges
Ignition and Turn Signal
Carpet

February 2003
Body to the painter
Carpet
Seat Harness
Final Seat Install
Shifter
Front & Rear Wheel Splash Guards
Lights and Accessory Wiring

March 2003
Completion 

No Later Than Goal is the 2003 Carlisle Car Show (May)


Home
The  Vision
Schedule


I missed my initial goal of completing the kit before the 2002 Carlisle Car Show.  I'm not really disappointed at missing that mark because my original intent was to enjoy the build and not make it a stressor in my life.  It's still importnant to have a general plan of action to keep this project on course so I've adjusted the schedule accordingly.